“We will continue with our projects, there will be no delays”, said Ismail Al Ramahi, manager gas processing division at ADNOC, while speaking to the participants of Gas Arabia 2009 conference, here in the capital.
The costs to construct oil and gas projects are sharply falling, as recession has hit global economies.
Already prices are 30 per cent cheaper than estimated last year, bringing new opportunities for Abu Dhabi National Oil Company (ADNOC) to step-up its efforts to expand its hydrocarbon infrastructure, in order to preparing for the next up-turn in the energy demand and the prices.
With the cost of development becoming more attractive, ADNOC official said
He expected the cost of projects to fell even to 50 per cent level from a 30 per cent at present, as economic gloom becomes thicker each passing day.
Abu Dhabi Onshore Oil Operations Company (Adco), the largest oil producer in the UAE last month awarded two EPC contracts to develop its Sahil, Asab and Shah onshore oilfields at a cost of $3.5 billion, about 20 per cent cheaper than estimated.
Economists are banking on
Al Ramahi invited international EPC contractors, technology and solution providers and consultants to get ready to bid for the large number of projects to be announced shortly.
In this regard, Al Ramahi said that the tenders of three mega projects would begin to come in large packages from next couple of months, as preparations in this regard are underway.
These multi-billion US dollar projects include Integrated Gas Development (IGD), Sour Gas Development, Nitrogen Generation and injection apart from Co2capture.
Other projects which are already in implementation stage include, Flare gas recovery project, besidesthe establishment of Compressed Natural Gas (CNG) stations across
On the Sour Gas Development project, which was estimated at $10-$12 billion, when it was announced late last year, in partnership with industry giant ConocoPhillips, the ADNOC official did not divulge on its currentestimated cost.
However, the project is nearing to complete FEED stage.
On the Nitrogen Generation and Injection project, he said that in the initial stage 300 million cubic feet per day (MCFD) of nitrogen gas will be injected into the oil reservoirs to enhance oil recovery, replacing the methane gas.
“And if the project bears positive results than the project will be expanded to 600 mmcfd”, he added.
Speaking on the Carbon dioxide Capture project with MASDAR, he said this multi-billion dollar project would inject CO2into the oil reservoirs to enhance oil recovery.
On the Flare Gas Recovery project, he said since 1995, there has been 74 per cent reduction in flaring which will be brought to zero–level.
The brand's success is driven by its dedication to maintaining the highest standards of purity and efficacy in its products
With Omron Complete, you can take control of your blood pressure and heart rhythm monitoring, reducing the need for emergency trips to the hospital
Combining advanced technology, world-class expertise, and personalised care, Burjeel Holdings’ hospitals lead in cutting-edge cardiac treatments
Learn how to take charge of your heart health and make informed choices for a healthier future with experts from Aster Hospitals and Clinics
Lower your risk of cardiovascular problems with simple steps
The UAE President acknowledged Trump's effort to bolster the partnership between the two countries
'This is a testament to how far we’ve come – from the desert to space', Dubai Ruler said during the call five years ago
From emptied accounts to fraudulent credit card charges, customers reportedly face blame and recovery agents — instead of solutions