Production at UK’s Laggan-Tormore gas fields delayed to 2015

Top Stories

Production at UK’s Laggan-Tormore gas fields delayed to 2015

Britain’s Laggan-Tormore gas condensate fields in the North Sea will start production next year, instead of at the end of this year, operator Total E&P UK told Reuters.

By Christopher Johnson (Reuters)

  • Follow us on
  • google-news
  • whatsapp
  • telegram

Published: Fri 29 Aug 2014, 10:49 PM

Last updated: Fri 3 Apr 2015, 9:51 PM

Total is developing the two fields off the Shetland Islands in Scotland at a cost of around £3.3 billion ($5.5 billion). As part of the project, the firm is constructing a gas processing plant and export pipeline.

Total E&P UK is the operator of the fields and holds an 80 per cent stake in the project, while Dong E&P UK has a 20 per cent stake.

“The plan is to finish construction of the project by year end. Once it’s at full production we anticipate [production of] 90,000 barrels of oil equivalent per day,” the Total spokesman said, without giving a reason for the delay.

However, in its interim results on Wednesday, Dong said the delay was linked to the construction of the gas treatment plant.

In addition, Dong said its Herje oil and gas field in the Danish sector of the North Sea would not start production until 2017, instead of 2016, due to delays by its suppliers.

Britain’s oil and gas output has fallen by around two thirds since 2000 as production has declined from ageing infrastructure.

Hopes for a revival have been pinned on significant capital investment over the past few years by oil and gas majors in new projects off the Shetlands and in field life extensions.