Dewa commissions new substation in Dubai South

Top Stories

Saeed Mohammed Al Tayer, MD and CEO of the Dubai Electricity and Water Authority (Dewa) has commissioned a new 400/132 kV substation in Dubai South.
It has a conversion capacity of 2020 megavolt-amperes (MVA) with 2.4 kilometres of 400kV overhead lines to connect with Dewa's network.
The project, with a total cost of Dh336.5 million was completed in a record time of 27 months. It included over 2.6 million safe working hours without injuries, despite the obstacles associated with the coronavirus epidemic during the final phases of the project. The latest technologies were used to follow work progress remotely according to the highest standards of safety and security to protect the health of all workers.
"We work in line with the vision and directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice-President and Prime Minister of the UAE and Ruler of Dubai, to provide an advanced and integrated infrastructure for electricity and water according to the highest standards of availability, reliability, efficiency, and safety. This meets the growing demand and keeps pace with the sustainable development needs of Dubai. Inaugurating the 400/132 kV substation in Dubai South is part of Dewa's efforts to increase the capacity and efficiency of the power transmission network in the area and meet the requirements of customers, developers, and the business sector, as well as the demand requirements of the new 132 kV stations at Dubai World Central," said Al Tayer.
Al Tayer noted that the total value of Dewa's power transmission network under construction exceeds Dh10 billion. He said that the substation in Dubai South was implemented according to the highest standards of quality, efficiency, and safety and uses the latest digital technologies. This supports Dewa's efforts to enhance digital transformation in all its services and operations.
Hussein Lootah, EVP of Transmission Power at Dewa, said that the new substation increases the total number of 400/132 kV substations to 23, in addition to four new substations being built and 250 kilometres 400 kV overhead transmission lines at an estimated cost of Dh2 billion. Dewa is currently conducting the final testing of 11 new 132/11 kV substations costing up to Dh1.5 billion.
The UAE, represented by Dewa, has maintained its first global ranking for the third consecutive year in 'Getting Electricity' as per the World Bank's Doing Business Report 2020, which measures the ease of doing business in 190 economies around the world. Dewa achieved 100 per cent in all of the 'Getting Electricity' indicators, including procedures; time; cost; and reliability of supply and transparency of tariff. Commercial and industrial customers can now get electricity connection up to 150kW within five days and in one step through Al Namoos, with security deposits and new connection charges waived. The UAE, represented by Dewa, has the shortest time in the world to get electricity according to the World Bank's report.
business@khaleejtimes.com

Published: Tue 28 Jul 2020, 6:01 PM

Updated: Tue 28 Jul 2020, 8:10 PM

  • By
  • Staff Report


Next Story